New construction – UFG Umformtechnik GmbH
May 2019
Preparations are running
The new building of UFG Umformtechnik GmbH is in full swing. Here you will soon receive more information.
We will also keep you up to date with impressions of the current construction measures.
August 2019
Production of the subgrade
Now it already looks like a construction site…
Excavators and bulldozers start the production of the subgrade.
It goes forward!
August 2019
view from above
From the bird’s eye view: In the most beautiful summer weather we are working hard on our new property… and week after week we are getting closer and closer to the actual start of construction.
August 2019
rest before the storm
Time to take a deep breath…
Now the floor is ready for the next construction phase. Let’s go!
August 2019
The lime layer
For optimal stabilization, a layer of lime is milled 40 cm deep into the ground and then smoothed.
This soil-lime mixture results in a solid base for our new production hall.
October 2019
The foundation
A lot has happened in the last weeks.
We have used the beautiful weather of the summer to prepare the ground for the start of construction of the production and administration building.
For a stable foundation, reinforcing steel cages
The construction of the hall begins
With a little delay, the next construction phase now begins – the building of the hall.
In the next few days, the steel construction, consisting of 80 tons of steel,
Built up step by step and welded to the foundation anchor plates.
March 2020
The interior fittings
The interior work is running at full speed!
The floor is now optimally prepared for further processing.
The underfloor heating has already been laid and then the concrete core activation was installed.
May 2019
The media pit is ready!
The media pit was completed.
July 2020
Tanks for oxygen and nitrogen
The two tanks for oxygen and nitrogen were installed and connected.